Well we are at the very exciting stage now. We had our PCI last week and were very impressed with how our PD SS handled the inspection, he agreed to pretty much all our requests. We had our independent inspector there at the same time as well and the SS handled that quite well too. Although I am sure the SS would have been happier without the inspector there. Our wonderful inspector - Andrew Forrester of Armaggedon Property Inspections (plug plug!!) - assured us that in his opinion the house was very well constructed, apart from some plaster issues. I can't say how pleasing that was to hear. It appears our money has been well spent after all!

It was a bit of a marathon effort though and we were there for over four hours going thru the issues. We had a very comprehensive list ourselves which helped ensure we didn't miss any of the little things. Most of our problems focused around the poor plaster but our SS has ensured us it will all be fixed by our handover tomorrow!
The other issues outstanding included
- painting
- crooked doorway arch
- crooked mirror
- broken door handle
- crooked power point
- very poor finish on all the grouting edges to showers and laundry tiles
- poor finish to the woodwork around the foyer
- broken base to front door
- unstable SS ballusters (some needed to be replaced with longer ballusters and needed to be glued in). Have to say our SS picked this up himself, we didn't even notice - thanks N
- very poor plaster to roof of foyer void - SS suggested we live with this for a while and he will come back at 3mth review and fix ALL of it. (..and yes, we believe he will come back)
...and a few other minor issues.

..and yes, by the time we finished the house did have the multicoloured measles! Pink for plaster, green for paint.

In the last week we have also had the fencing completed by Mick Anthony who has done a terrific job. Great price, great workmanship and prompt service.

We have also organised the window furnishings which will be installed on Monday. At this point we would have to thoroughly recommend Interlux Designs in Berwick. They are so helpful and professional with great supportive ideas and a very prompt service. We had the measure on Monday and they are going to fit a week later! You couldn't ask for more.

Carpets are booked for Friday and Saturday (Glendale Carpets Hallam) and antenna for tomorrow afternoon (All Aussie Antennas). There seriously is SO much to organise!

And finally, just to make things interesting we had a bit of a stress out today when the bank incorrectly posted our final cheque in the mail instead of letting us pick it up today at the bank. After a quick check of the mail box by our dear neighbour, we realised there was no cheque in sight! Of course it was then back to the bank for both of us with our grumpy faces on. After first being told we could get a replacement cheque in, wait for it, 10 DAYS!!! common sense prevailed and we were given a replacement cheque. You really don't need that the day before settlement. Our advice is to make sure you organise your final cheque two weeks before handover. We left 9 days but this obviously was not enough time!!

So it is one more sleep and dream home here we come. It seems to have been a very long wait and we are so glad it is coming to an end.

Will post some pics tomorrow when it is officially ours!

5 comments:

NoShitSherlock said...

Once again, I can't believe how excited I am getting over a complete stranger's house! Really, it seems like most of the problems are minor and easily rectified. I can only hope that our build continues ro run as smoothly.
It doesn't surprise me about the bank cheque, you'd think they'd know what they were doing by now...
Good luck with the big move and if any of your furniture doesn't look fabulous in your fabulous new house, then chuck it out and get some fabulous new stuff!

BelleBeau said...

Congratulations, I'm excited for you guys too. Bet you can't believe it is going to be over. Building a house takes over your life! Good to hear PD are going to fix your issues too
Cheers
J

M&J said...
This comment has been removed by the author.
M&J said...

Congrats guys!!! How did handover go? So happy for you and great to hear only minor issues need fixing. Hope you enjoy your beautiful new house and hope the move isn't too hectic.

NoShitSherlock said...

Hi Gang,
I'm having a bit of a problem with, guess what - the staircase!! Can you tell me what you are doing with your 'stringers'? We've decided to stain our treads, handrail and bottom rail, with painted risers, but we just got a call to ask us whether we wanted the 'stringers' painted(free) or stained ($385). From what I can gather, the stringer is the strip of wood that runs down the side of the staircase below the bottom rail and I don't know whether to stain it to match the bottom rail, or paint it to blend in with the wall... I hope you understand 'cos I'm struggling... Please help!!!
P.S - If you are too busy with the move and haven't had time to read this I totally understand :)

My slideshow